Harbour Regeneration Plans
Following Planning Approval being granted for the Harbour's Regeneration Plans, detailed work has commenced to begin construction in September 2022.
Phasing of the overall project is as outlined below (subject to alteration):
Phase 1 - the admin/facilities complex, new sewerage treatment plant and sea wall at the Duver, and associated car parking. Construction to commence in September 2022 - completion March 2023. To see a plan click Duver Marina Plan.
To follow on:
Phase 2 - Bembridge Marina car park and floating facilities.
Phase 3 - Ex-silt lagoon site for mitigation purposes.
Phase 4 - New residential scheme at the Duver.
Phase 5 - New residential scheme at the Marina [(note: Phases 4 and 5 may be switched around).
The main contractor appointed is: John Peck Construction Ltd.