Regeneration Plans


Harbour Regeneration Plans


Following Planning Approval being granted for the Harbour's Regeneration Plans, detailed work has commenced to begin construction in September 2022.   

Phasing of the overall project is as outlined below (subject to alteration):

Phase 1 - the admin/facilities complex, new sewerage treatment plant and sea wall at the Duver, and associated car parking.  Construction to commence in September 2022 - completion March 2023.  To see a plan click Duver Marina Plan.

To follow on:

Phase 2 - Bembridge Marina car park and floating facilities

Phase 3 - Ex-silt lagoon site for mitigation purposes.

Phase 4
 -
New residential scheme at the Duver.

Phase 5 - New residential scheme at the Marina [(note: Phases 4 and 5 may be switched around).

The main contractor appointed is: John Peck Construction Ltd.
     

 

 

 






SUBSCRIBE TO OUR NEWSLETTER

ON THE WIND

SIGN UP TO RECEIVE THE LATEST NEWS AND OFFERS
FROM BEMBRIDGE HARBOUR









Bembridge Harbour



DETAILS

The Duver, St Helens
Isle of Wight, PO33 1YB

Phone: +44 (0) 1983 872 828

Email: office@bembridgeharbour.co.uk


WEATHER IN BEMBRIDGE (°C)

14.44°

Min: 11.7°

Max: 15.44°

Tue

Min: 

13.85°

Max: 

16.86°

Wed

Min: 

13.94°

Max: 

16.17°

Thu

Min: 

13.67°

Max: 

15.86°

Fri

Min: 

13.63°

Max: 

16.45°

clear sky

Humidity: 89 %

Wind: 0.89 m/s

Visibility: 10 km






  • Login